Client: Coca-cola, East Kilbride - Re-roof

Contract: NEC 3 Option. A

Value: £400k

Duration of Project: 12 weeks

hcm projects completed their fourth project for Coca Cola Enterprises (CCE) building at their East Kilbride production facility within budget and to programme.

The works involve the removal of the existing roof and replacing it with a profile metal sheeting and insulation material.

The works also included the removal of all “Galbestos” sheeting throughout the site, providing suitable containment and removal of the redundant materials from site.

All the above works were carried out whilst the production facility remained operational.

Our experience