January 2012

hcm projects have now completed this initial 21 week contract, value £3.65m for Asda to the former Netto warehouse at South Elmsall.
The work consists of the refurbishment to this former Netto distribution centre to allow Asda to operate this warehouse as a chilled and ambient cross dock (XDC) facility.
This 249,000 sq.ft. building will now incorporate 34 dock doors, 4 freezer doors, 20 double deck doors and 8 level access doors.

Other works consist of:
Removal of existing warehouse racking, demolition of the front of the building to faciltlitate new access doors, new refrigeration plant, upgrade of transport and main offices, extensive civil/structural works  for new access doors, new sprinkler system and upgrade to the M&E services throughout.